Bayview Biomedical Research Center (BRC) Project: Additional Questions and
Answers

Question: What is the total lease cost?

Answer: The annual lease payment is $13,253,000 for the entire project. This lease cost
does not include the operating expenses. The breakdown of this annual lease cost is as
follows:
$12,373,000 Debt Service for the loan
400,000 Ground Rent to FSK Land
240,000 Capital Repair Reserve
240,000 Estimated insurance cost

Based on the government lease, a favorable, below-market financing was arranged for the
loan. The NIA's portion of the annual lease payment is approximately $6.7 million and
the NIDA's portion is $6.0 million with the remaining $0.57 million is for the Director's
Reserve Space.

Question
: How many waivers from the NIH Research Design Requirements were
granted? Who approved those waivers? Also, I still would like to know specifically
what variances to the fire code were granted

Answer: As previously stated, it was not a requirement that this project design comply
with the NIH Design Requirements Manual due to the fact that NIH will not own the
facility. Had this design been for an NIH owned facility on NIH land, it would have been
subject to the Design Requirements Manual and any variances would have been
administered in accordance with the applicable procedures. Another pertinent point is
that NIH does not have code jurisdiction over this property. Had variances been
submitted to the NIH Fire Marshal, for example, he would not have had the authority to
approve or disapprove them. Therefore, no specific variances or waivers relative to the
BRC facility were processed by NIH. It is important to note that the facility does comply
with all applicable building codes and that there were no compromises in life safety
issues. These applicable building codes are very comprehensive. For example, the
International Building Code is 660 pages long and it references other applicable codes
such as the International Electrical Code, the International Fuel Gas Code, the
International Mechanical Code the International Plumbing Code, the International Energy
Conservation Code.

Relative to variances to the governing Maryland and Baltimore codes, in addition to the
NFPA 45 design criteria for chemical storage, other variances were requested and
obtained. The variance procedure is typically one in which the designer meets the
intentions of the code via a different approach, or seeks to identify why any unique
features of the facility require special consideration. The variance process allows the
designer to meet the intention of the code with an alternative method that preserves life
safety. In addition to the variances, there were a few code interpretations. The number

1

of variances (7) and interpretations (5) is within the average, based upon a comparison of
projects of similar size and complexity. Following are the variances and interpretations
that were approved.

Variance: Permission granted to omit fire dampers in hazardous exhaust ducts permitted
without waiver. This was actually just a clarification of the existing code. Specifically,
normal HVAC ductwork contains dampers that close in the presence of smoke. In the
case of fume hoods that routinely exhaust smoke, such closure would impact their
functionality by closing the damper and allowing fume buildup, negating the
functionality of the fume hood. This variance was approved by the City of Baltimore.

Variance: A second variance was submitted for eliminating smoke dampers for the same
justification as submitted above. This variance was approved by the City of Baltimore.

Variance: Another variance involved the substitution of a 1 hour atrium separation with
water curtain for 2 hour control area separations at atrium areas 5 and 6. Stated
differently, in lieu of constructing a wall with a 1 hour fire rating, the area was protected
via a more robust sprinkler system to a 2 hour standard. This would contain the fire for 2
hours (in lieu of the code requirement of 1 hour). This variance was approved by the City
of Baltimore.

Variance: Permission was granted to store small quantities of Class I flammable liquids
in the basement. The Fire Marshal reviewed the types and quantities of liquids and
approved this. As an example, the Nuclear Magnetic Resonance clinic requires small
quantities of ethyl alcohol, acetone and electric contact cleaner. This variance was
approved by the City of Baltimore.

Variance: Permission granted to locate Class I standpipe hose connection at the floor
level in lieu of at the intermediate landing in stair enclosures. The firefighters actually
preferred to have the standpipe hose connection at the floor level (instead of at the
intermediate landing) to provide them more room to maneuver with the hoses. This
variance was approved by the City of Baltimore.

Variance: Permission granted to protect hazardous exhaust duct penetrations with
sprinklers in lieu of rated construction. This variance was approved by the City of
Baltimore.

Variance: Permission was granted to allow 3 laboratory units on floors 5, 6 and 8. The
code normally allows 2 per floor. On those floors, NIA has two labs and NIDA has one,
for a total of three. This variance was granted because the code presumes that the facility
is singular, but this facility consists of two towers and the towers have adequate
separation between them. This variance was approved by the City of Baltimore.


2

Variance: Permission granted to allow both Level 1 and Level 2 to be classified as
“Level 1 Above Grade” per Table 414.2.2. This variance was approved by the City of
Baltimore.

Interpretation: In the Integrated Utility Plant, permission was granted to utilize the
freight elevator as the handicap accessible elevator to the second floor and loading dock.
It is anticipated that the use of an elevator by a handicapped utility operator would be
limited and that such a need could be satisfied by use of the freight elevator. This
variance was approved by the Maryland Codes Administration.

Interpretation: Permission granted to make 2 of 3 required exits handicap accessible in
lieu of all 3 at Level 3 entry plaza. This variance was approved by the Maryland Codes
Administration.

Interpretation: Permission granted to use “Bio-bubble” animal cage enclosures within
building. At the request of NIA, we constructed a plastic bubble animal holding room in
the vivarium. This unique feature required a code interpretation. This variance was
approved by the City of Baltimore.

Interpretation: Permission was granted to lock egress side of Seclusion Room 02BB09
with provision of unlocking upon fire alarm activation. A Seclusion Room is a
permission granted to classify as part of Institutional Use. This room was intended to be
constructed for NIDA outpatient clinic and was intended to ensure that a patient under
observation. Subsequently, NIDA decided that the Seclusion Room was not required and
the Seclusion Room was omitted. This variance was approved by the City of Baltimore
Fire Marshal.

Interpretation: Permission was granted to provide no internal access to atrium roof.
The code requires such an access ladder because it is presumed that the roof has
mechanical equipment on and that maintenance personnel will need to access it. This
roof has no mechanical equipment, so such a fixed internal entrance was not required.
This variance was approved by the City of Baltimore Fire Marshal.

-----------------------------------------------

Question: On the rent, my understanding is that the $13.2 million annually will come
out of the research budget and not the capital budget. Is that correct?
Answer: Rent will come out of the IC operating budget, not the capital (Buildings &
Facilities) budget, in keeping with NIH-wide budgeting and accounting practices. To the
best of our knowledge, all Federal agencies follow this same process; that is, using
operating dollars to pay for leases.

Question: Also are there any other annual fees on top of the $13.2 million?
Answer: $13.2 million is the lease contract rent for the debt service, ground rent,
insurance and capital repair reserve for the entire project. In addition to this “contract

3

rent”, there will be the building operation and maintenance expenses which are estimated
to be in the range of $16M and $18M per year depending on the cost of utilities. Utilities
costs have increased significantly over recent years due to market volatility, impacting
private and public enterprises.

Question
: Who or what is the lessor? Who gets the $13.2 million per year?
Answer: The lease is with BRC Lease Co. LLC, a special purpose entity created to
guarantee repayment of $200 million loan to finance the project. BRC Lease Co. will
collect the contract rent ($13.2M) from NIH and disburse it to the lender, the insurance
company, and Johns Hopkins for the ground lease.

Question: Was not the decision not to anchor the foundation to bedrock due to the fact
that the building sits on top of a former landfill site? If the site was so stable, why were
there repeated collapses on the foundation site during early construction and why was a
retaining wall constructed to prevent further collapses?

Answer
: The building is not sited on top of a former landfill. Perhaps this thought arose
from the fact that a parcel to the north of the BRC site was once used by Johns Hopkins
as a landfill. Based on the geotechnical analysis of the site, the building foundation is
designed to be spread footings, which are approximately 45 feet below grade where the
ground compaction is such that it can support the building load imposed on the footings.
The spread footing foundations never collapsed. The sheeting and shoring retaining wall
moved approximately 1.5” to 2.5” during the early phase of construction. This wall had
nothing to do with the foundation and never collapsed. However, while the contractor
was forming the building basement concrete wall and while the cause of the shifting of
the retaining wall was being investigated, the contractor decided to further reinforce the
wall as a precautionary measure.


4

Bayview Biomedical Research Center (BRC) Project Chronology

September 1998
: NIH, with substantial input from the Institutes and their Scientific
Directors, conducted a Facility Feasibility Study. The study ultimately recommended a
consolidated replacement facility for NIA and NIDA. The study did not specifically
describe whether such a replacement facility should be owned or leased. An alternative
option of renovating the existing facilities was considered but deemed inadequate for a
number of reasons including lack of swing space, substantial disruption to sensitive
research programs, little opportunity for consolidation or joint use of facilities, little or no
expansion capability, and protracted construction phasing and cost. The studies showed
that these existing facilities were obsolete and did not meet the present needs of the
institutes, let alone their needs for the 21st century.

September 1998: NIH Director Review:
The studies were reviewed with then-Director
of NIH, Dr. Harold Varmus, and he agreed with the recommendation for a new
NIA/NIDA facility on the Bayview Campus. Dr. Varmus also considered a number of
transaction structures to implement the project. He ultimately approved a transaction
structure consisting of a lease from JHU to NIH that would balance the up-front planning
costs by NIH with the best overall rent structure over the term of the lease while still
assuring the appropriate level of quality for the building.
January 1999: GSA awarded contract to Dome Real Estate of Johns Hopkins University
to develop a concept plan for the new Bayview project.
February 1999: Dome selected the architectural firm, HLM Design, to prepare the
concept design.
October 1999: Dome Real Estate developed a Business Plan and Project Budget to seek
project authorization via GSA/OMB and Congress. HLM completes Concept Design.
June 2000: GSA Mid-Atlantic submitted prospectus to GSA Central Office, proposing a
replacement lease of 392,482 rentable square feet of laboratory, office and related spaces
for NIH.

June 2000
: Basis of Construction Cost for Concept Design, Scoring Analysis and
Construction Cost submitted by Dome to NIH.

June 21, 2000: Congressman Shuster Briefing by Mr. Steve Ficca, Director of the Office
of Research Services. (Congressman Shuster was the chairman of Committee on
Transportation and Infrastructure), focusing on the need for new NIA and NIDA
facilities. Justification included the 30-year old buildings needing extensive HVAC
upgrading.

June 29, 2000: GSA engaged Dome for Schematic Design with HLM as the prime
Architects.

5

July 26, 2000: House Committee on Transportation and Infrastructure requests Report
on the Project pursuant to Section 11(b) of the Public Building Act.

September 2000: GSA Central submitted via OMB a report to Congress under Section
11(b) of the Public Buildings Act confirming the need for a new leased NIA/NIDA
facility. NIH coordinated on this action.

September 19, 2000
: GSA forwarded the 11B Report to House Committee on
Transportation and Infrastructure.

October 20, 2000: Mr. Steve Ficca, Director of the Office of Research Services met with
the staff of Senate Committee on Public Buildings to discuss the project.

December 2000
: The Consolidated Appropriations Act for FY 2001 authorizes a lease at
Bayview Campus in Baltimore, Maryland.

February 2001: HLM completed Schematic Design

June 2001: Lease signed by among NIH, FSK Land Corporation (a Hopkins Entity), and
BRC Lease Co (the Lessor). Mr. Joe Friel, a Contracting Officer, signed the lease on
behalf of NIH.

Summer 2001: Johns Hopkins Real Estate & NIH ORF Project Team selected Smith
Management Construction Inc. (SMCI) as the project Development Manager.

September 17, 2001: Development Management Agreement approved between BRC
Lease Co. (a Special Purpose Entity serving as Lessor) and SMCI.

February 2002
: CUH2A was selected by NIH ORF Project Team/SMC/BRC Lease Co.
to design the facility.

June 2002: Skanska USA was selected by NIH ORF Project Team/SMCI/BRC Lease
Co. as the project Construction Manager.

June 26, 2002: 15% Design completed. NIH User ICs and NIH ORF Project Team
reviewed and provided comments.

October 2, 2002: 35% Design completed. NIH User ICs and NIH ORF Project Team
reviewed and provided comments.

February 14, 2003: 65% Design completed. NIH User ICs approved and signed-off on
these documents. ORF Project Team provided comments and approved with the
stipulation that comments would be incorporated in the subsequent submission.


6

June 2, 2003: Construction Documents submitted to Baltimore City for Building Permit
Review (minimum 90-day process) by Smith Management Construction Inc. (SMCI), the
Development Manager.

August 2003: Guaranteed Maximum Price (GMP) received from Skanska USA by
SMCI. NIH and BRC Lease Co. were copied.

April 15, 2004: Guaranteed Maximum Price approved by SMCI in consultation with
NIH

April 30, 2004:
Bid Documents completed.

May 20, 2004: Skanska awarded construction subcontracts to various trade
subcontractors and issued notice-to-proceed.

May 21, 2004
: Construction site preparation started.

October 12, 2004: Ground Breaking Ceremony.

August 2005: Steel structure topped out.



7